For connections 3″ or larger: Complete and submit a New Water Connection Request form when ready for new service.

Please anticipate a 10-12 week lead time from the date of your request to the date of installation.

Before scheduling, you must have the following:

  • Approved Utility Plan
  • Water Connection Permit

Purchasing a new water connection permit does not initiate the scheduling process!

▶ To schedule your connection:

  1. Complete the New Water Connection Request Form, provided, with your approved utility plan and connection permit
  2. Email the completed form to PWD_Water_Connections@phila.gov

You’ll receive a confirmation email with the details needed to follow up on the status of your request.