Northeast Philadelphia, Rhawnhurst
Benton / Solly
Overview
Project #20582 Benton / Solly will replace water mains in the Rhawnhurst neighborhood.
Streets Affected
| Street | Segment | Type of Work |
|---|---|---|
| Solly Ave. | from Eastwood St. to Roosevelt Blvd. | |
| Eastwood St. | from Stanwood St. to Solly Ave. | |
| Arthur St. | from Eastwood St. to Bradford St. | |
| Leonard St. | from Stanwood St. to Solly Ave. | |
| Evarts St. | from Benton Ave. to Tolbut St. | |
| Tolbut St. | from Evarts St. to Castor Ave. | |
| Benton Ave. | from Evarts St. to Castor Ave. |
For worksite issues, contact:
- Abraham Mathews
Inspector (on-site)
abraham.mathews@phila.gov
267-401-5429 - Joe Gaydosh
Project Engineer
Joseph.F.GaydoshJr@Phila.gov
267-408-4819 - Gary Seifert
Division Engineer
Gary.J.Seifert@phila.gov
215-685-6363 - Seravalli Construction Inc.
Contractor
john.seravalli@seravalli.com
-
For more information, contact:
- Amy Hopf
PWD Construction Liaison
water.construction@phila.gov