Cedar Park 1

Skip to Updates ↓

Current Phase:

Start:

January 2020

Completion:

Anticipated March 2021

Cedar Park GSI Map

Overview

Project #50162 (Cedar Park 1) will implement green infrastructure to improve the stormwater management of the Cedar Park. This is part of the overall Green Infrastructure Initiative implemented by City of Philadelphia called Green City, Clean Waters – #50162 is part 1 of two GSI projects in Cedar Park.

Streets Affected

  • 53rd Street from Cedar Avenue to Baltimore Avenue
  • Cedar Avenue from 53rd Street to 51st Street
  • Walton Avenue from 53rd Street to 51st Street
  • Catharine Street from 52nd Street to 50th Street
  • 51st Street from Cedar Avenue to Baltimore Avenue
For worksite issues, contact:
For more information, contact:

Project #50162

Project Type
Watershed
ZIP Code
Council District

Project Files

50162_FactsheetOctober 23, 2020 50162_LetterOctober 23, 2020

Updates

Construction substantially complete

Construction for project #50162 substantially complete. A few punchlist tasks remain.

Posted by:
Amy Hopf
Category:
Project Update

Construction Resumed

Following Governor Tom Wolf’s announcement that construction activities across the state would be allowed to resume, work for this project was able to resume.

This resumption follows a construction freeze of all non-emergency work that was put in place on March 20, 2020.

Your health and safety is our priority at all worksites. Our teams are utilizing protective equipment, sanitizing procedures and social distancing. PWD is committed to ensuring a safe workplace for all PWD employees and protecting their health.

To report construction‑related incidents or issues requiring immediate attention, please call 215‑685‑6300.