Current Phase:

Start:

November 2023

Completion:

Estimated October 2024

Overview

Project #20525 Broad / Carlisle will replace water mains in the Yorktown neighborhood of North Philadelphia.

Streets Affected

  • Jefferson St. from N. Broad St. to N. 12th St.
  • Master St. from N. 16th St. to N. 15th St.
  • Master St. from N. Broad St. to N. 13th St.
  • Thompson St. from N. 17th St. to N. Broad St.
  • N. Carlisle St. from Poplar St. to W. Girard Ave.
  • N. Broad St. from Thompson St. to Master St.
For worksite issues, contact:
For more information, contact:

Project #20525

Project Type
ZIP Codes
Council District

Project Files

#20525 Construction LetterSeptember 13, 2023

Updates

Community meeting with United Francisville Civic Association: Wed, December 13

The Philadelphia Water Department will join United Francisville Civic Association’s community meeting to share a project update on Wednesday, December 13, 2023 at 6:30pm.

The meeting will be held at Francisville Recreation Center: 1750 Wylie St, Philadelphia, PA 19130.

This community meeting will review the installation of new water mains in the North Central Philadelphia and share construction updates.

Posted by:
Amy Hopf
Category:
Project Update

Construction starting along Jefferson St

Construction started for project #20525 along Jefferson St. between N. 12th St. and Broad St. Work began on 11/13/23 and is expected to be complete in Fall 2024.

Tentative schedule:

  • Master St from 13th to 16th: Jan & Feb 2024
  • Thompson St from 15th to 17th: March & April 2024
  • Broad St, Carlisle St, and Burns St: to follow