1. The new water mains have been installed but have not been connected yet.
  2. Mains must go through a series of tests before we can put them in service and connect them to the customers’ properties.
  3. The timing of this connection work is coordinated with the customer in advance.
  4. Street restoration is the final step.

Danella Companies (Hired Contractor) have provided the following estimated schedule*:

  • Testing of new water mains: through November
  • Connection to service lines: end of November – December
  • Final tie-in: early December

* The estimated schedule depends on the results of the tests.