Construction Update for Project #20464
- The new water mains have been installed but have not been connected yet.
- Mains must go through a series of tests before we can put them in service and connect them to the customers’ properties.
- The timing of this connection work is coordinated with the customer in advance.
- Street restoration is the final step.
Danella Companies (Hired Contractor) have provided the following estimated schedule*:
- Testing of new water mains: through November
- Connection to service lines: end of November – December
- Final tie-in: early December
* The estimated schedule depends on the results of the tests.