As of mid-December, work to replace the water main along S 22nd is about 75% complete and is estimated to be complete by mid-January 2024.

The sewer work will begin immediately after and is scheduled to take 5 weeks to complete. Re-paving will follow the sewer work.

With no unanticipated delays, the project will be complete by late February 2024.