South Philadelphia, Southeast Philadelphia, Whitman
Fitzgerald / American
Overview
Project #40981 Fitzgerald / American will replace water and sewer mains in the Whitman neighborhood of South Philadelphia.
The Water Department will have an assigned engineer and inspector for the project, who will be on-site every day. For on-site problems/questions, please talk with the inspector or engineer on the job site. Contact information will be listed below when construction is nearing.
Water shut-offs are required for this work and typically start at 9am, lasting 2 to 8 hours.
Streets Affected
- Fitzgerald St. from S. 5th St. to S. 3rd St.
- S. American St. from Ritner St. to Wolf St.
- Daly St. from S. 2nd St. to S. Front St.
- S. Reese St. from Shunk St. to Porter St.
For worksite issues, contact:
- Yash Roy
Inspector (on-site)
yroy@aegroup-llc.com - Anoop George
Project Engineer
george.anoop@phila.gov
215-301-5494 - Dave Pandya
Division Engineer
Dave.Pandya@phila.gov
215-685-6352
For more information, contact:
- Amy Hopf
PWD Construction Liaison
water.construction@phila.gov