,

Buckley Terrace Storm Flood Relief

Current Phase:

Start:

Estimated Fall 2024

Completion:

Estimated Summer 2027

Overview

Project #41186 Buckley Terrace Storm Flood Relief (SFR) will replace a water main and sewer in the Bustleton neighborhood of Northeast Philadelphia.

This work will relief flooding in the Buckley Terrace cul-de-sac.

The Water Department will have an assigned engineer and inspector for the project, who will be on-site every day. For on-site problems/questions, please talk with the inspector or engineer on the job site.

Customers may experience limited water interruptions during construction.

Streets Affected

  • Buckley Drive from Pine Road to Sandanne Road
  • Buckley Terrace from Buckley Place to Cul-de-sac
  • Drainage right-of-way from Buckley Drive to Shelly Lane
  • Shelly Lane from Beth Drive / Stratford Drive to Cul-de-sac
For worksite issues, contact:
For more information, contact:

Project #41186

Project Type
ZIP Code
Council District

Project Files

#41186 Construction LetterAugust 7, 2024
Jump to Top