Church / Belfield

Skip to Updates ↓

Current Phase:

Start:

January 2022

Completion:

Estimated Summer 2022

Overview

Project #41178 Church / Belfield is an emergency sewer replacement project that will replace sewer pipes in the East Germantown neighborhood.

Streets Affected

Street Segment Type of Work
Intersection of Church Lane and Baynton St./Belfield Ave.
For worksite issues, contact:
For more information, contact:

Project #41178

Project Type
ZIP Code
Council District

Project Files

41178 Construction LetterDecember 14, 2021

Updates

Construction began

Construction for this project began January 4th, 2022.