Manayunk, Northwest Philadelphia
Flat Rock Dam Betterment
November 2024 Project Completion Update
The Flat Rock Dam Betterment Project (Project No. #60006) is approaching the end of its construction work. While the project was expected to complete construction by Fall 2024, work is now expected to be completed by Spring 2025. This is due to unforeseen delays throughout the 2.5 years of active work.
Helpful timeline information:
- Active construction will continue through the winter with the removal of the temporary cofferdam.
- There will be a series of safety and quality tests performed throughout the winter that will ensure the proper restoration of water flow to the Manayunk Canal.
- New greenery will be planted in Spring 2025 during the April-June planting season.
PWD will host a ribbon-cutting event in Late Spring 2025. There will be more information about this to come.
We thank the engineers, contractors, and the engaged community for their patience and support throughout this important project. For further details or questions, please feel free to reach out to our project team.
Read more about the history of the project.
__________________________________________________________
Overview
The Flat Rock Dam Betterment project will reconnect the Manayunk Canal with the Schuylkill River at Flat Rock Dam to improve local water quality.
The work includes the construction of new structures connecting the waterways, improvement of existing structures, and the stabilization and preservation of historic elements at the Feeder Gate House building. A new intake system will control the flow of water into the canal as needed.
Additional improvements at this site include:
- Green infrastructure managing stormwater at the site
- Improved security with perimeter fence
- Educational signage and graffiti removal
- Preservation and display of historic iron gearboxes through the Percent For Art program
- Improved access for maintenance and cleaning at the site
There are no local roadway closures anticipated. Some portions of the Schuylkill River Trail in this area may have limited access during construction. There are no anticipated impacts on parking.
______________________________________________________
Previous Project Updates
March 2024 SRT Reopening Update:
The closed trail section between the Manayunk Towpath and Shawmont will officially reopen on Saturday, March 30, 2024.
January 2024 SRT Closure Update:
Due to conditions at the site, work for the Flat Rock Dam Betterment project has been delayed. The concrete work that requires the trail closure has not been completed, and the trail closure will be extended through March 2024. The trail is now expected to reopen on March 30, 2024.
August 2023 Schuylkill River Trail Closure Announcement:
Starting on Monday, September 11, 2023, the Schuylkill River Trail (SRT) alongside the Flat Rock Dam between Leverington Ave. in Manayunk and Shawmont Station will be closed to all pedestrians and bikers.
Temporary suspension of trail use is necessary for pedestrian and biker safety as the work along the steep embankment is completed. This work requires concrete pouring that needs to occur during warmer weather, and cannot occur during the winter.
During this time, you will notice closure signs on both ends of the obstructed portion: one at the Shawmont Station at Shawmont Ave. and Nixon St., and one just below Leverington Ave. on the Manayunk Towpath. Walkers and bikers will be able to travel further on the SRT toward the worksite but will meet a dead end at the worksite and will be required to turn around.
See the mapped detour route here:
Read more about the closure on our recent blog post.
For worksite issues, contact:
- Thomas McIntyre
Inspector (on-site)
tmcintyre@jbcassociates.com - Ian McKane
Project Engineer
Ian.McKane@phila.gov
267-250-1816 - Peter Reilly
Division Engineer
Peter.Reilly@phila.gov
215-200-1539
For more information, contact:
- Amy Hopf
PWD Construction Liaison
water.construction@phila.gov