,

Bambrey / Stillman

Current Phase:

Start:

March 2025

Overview

Project #40925 Bambrey / Stillman will replace water and sewer mains infrastructure in the Allegheny West neighborhood in North Philadelphia. Work is estimated to start in 2025.

The map above shows where new water mains will be installed and the service lines connected to the new mains. These properties may experience limited water interruptions during construction.

An assigned PWD inspector and engineer will be on-site and can answer questions about the work. Inspector and engineer contact information will be listed below when construction is nearing.

Streets Affected

Street Segment Type of Work
N. Bambrey St. from W. Allegheny Ave. to W. Clearfield St.New Water Main, New Sewer
N. Stillman St. from W. Indiana Ave. to W. Willard St.New Water Main, New Sewer
W. Toronto St. from N. 25th St. to N. 24th St.New Water Main, New Sewer
W. Hilton St. from N. 25th St. to Fox St.New Water Main, New Sewer
For worksite issues, contact:
For more information, contact:

Project #40925

ZIP Codes

Project Files

Project #40925 Pre-Construction LetterDecember 27, 2024
Jump to Top