Fitzgerald / American

Skip to Updates ↓

Current Phase:

Start:

October 2024

Completion:

Estimated July 2025

Overview

Project #40981 Fitzgerald / American will replace water and sewer mains in the Whitman neighborhood of South Philadelphia.

The Water Department will have an assigned engineer and inspector for the project, who will be on-site every day. For on-site problems/questions, please talk with the inspector or engineer on the job site. Contact information will be listed below when construction is nearing.

Water shut-offs are required for this work and typically start at 9am, lasting 2 to 8 hours.

Streets Affected

  • Fitzgerald St. from S. 5th St. to S. 3rd St.
  • S. American St. from Ritner St. to Wolf St.
  • Daly St. from S. 2nd St. to S. Front St.
  • S. Reese St. from Shunk St. to Porter St.
For worksite issues, contact:
For more information, contact:

Project #40981

Project Type
ZIP Code
Council District

Project Files

40981 Construction LetterJuly 18, 2024

Updates

Southeast Philadelphia Projects Community Meeting Update

Curious about how water work in Southeast Philly?

Join PWD at Whitman Council’s monthly meeting to learn more.

Date: Wednesday, November 20th, 2024
Time: 6:30pm
Location: Brian Donnelly Funeral Home, 2239 S 3rd St, Phila, PA 19148

 

Visit the Southeast Project Page for construction info for all Planned Projects: water.phila.gov/southeast

Each Project Page has:
– Schedules and phases for each project: Find out when construction is planned.
– Points of Contact: Get in touch for questions or issues.
– Construction Letters: See copies of important info for residents about potential service interruptions, parking and more.

RSVP on the Facebook event.

Posted by:
Amy Hopf
Category:
Project Update

Construction started for Project #40981

Project #40981 mobilized on September 30, 2024. 4 Blocks of proposed water main and sewer replacements: One block has completed main installation, passed sample approval, and is making service line connections.