SAP5 Priority Reconstruction Work

Current Phase:

Estimated Start:

January 2026

Estimated Completion:

Early 2027

Overview

Project #41209 SAP5 Priority Reconstruction Work is a planned PWD project in various areas of Philadelphia. It will build new water mains and sewers.

An assigned PWD inspector and engineer will be on-site and can answer questions about the work. Construction contact information and streets affected are listed below.

For more information, please email the PWD community outreach team at water.projects@phila.gov. Please specify the project name, project number, and ZIP code in your email.

Streets Affected

Street Segment Type of Work
W. Lycoming St. from S. 5th St. to S. 7th St.New Water Main
W. Lycoming St. from N. 6th St. to N. Marshall St.New Water Main, New Sewer
S. 5th St. from Wolf St. to Jackson St.New Water Main, New Sewer
Ross St. from E. Sharpnack St. to E. Springer St. New Water Main, New Sewer
S. Dover St. from Oakford St. to Wharton St.New Water Main, New Sewer
Larkspur St. from Kelvin Ave. to Stevens Rd.New Water Main, New Sewer
Sears St. from S. 21st St. to S. 22nd St.New Sewer
For worksite issues, contact:
For more information, contact:

Project #41209

Project Files

Project #41209 Construction LetterFebruary 20, 2026 Project #41209 Maps: Page 2January 15, 2026 Project #41209 Maps: Page 1January 15, 2026