Awbury Rec Center

Skip to Updates ↓

Current Phase:

Start:

October 2022

Completion:

Estimated September 2023

Overview

Project #50241 (Awbury Rec Center) will implement green infrastructure to improve the stormwater management in the East Germantown neighborhood.

This is part of the overall Green Infrastructure Initiative implemented by City of Philadelphia called Green City, Clean Waters.

Streets Affected

  • Awbury Rec Center/Park
  • Ardleigh St. from E. Washington Lane to E. Haines St.
For worksite issues, contact:
For more information, contact:

Project #50241

Project Type
ZIP Code
Council District

Project Files

50241 Construction LetterAugust 23, 2022 #50241 Bid Outreach LetterJune 21, 2022

Updates

Construction starting

Construction activities started on October 17, 2022 for Project #50241, Awbury Rec Center.

Posted by:
Amy Hopf
Category:
Project Update

Cliveden Hills Association community meeting

PWD attended Cliveden Hills Association’s June community meeting to share info about the project.