Berks / Montgomery

Skip to Updates ↓

Current Phase:

Start:

April 2023

Completion:

Fall 2024

Overview

Project #20437 Berks / Montgomery will replace water mains in the Norris Square neighborhood in North Philadelphia.

Streets Affected

Street Segment Type of Work
Cecil B. Moore Ave. from N. 7th St. to N. 6th St.
N. 6th St. from Cecil B. Moore Ave. to Diamond St.
W. Montgomery Ave. from N. 6th St. to N. 10th St.
W. Berks St. from N. 5th St. to N. 8th St.
N. 8th St. from W. Montgomery Ave. to Cecil B. Moore Ave.
N. 9th St. from W. Montgomery Ave. to Cecil B. Moore Ave.
N. 5th St. from W. Berks St. to W. Norris St.
For worksite issues, contact:
For more information, contact:

Project #20437

ZIP Code

Project Files

#20437 Construction LetterMarch 9, 2023

Updates

Work began for project #20437

Work for project #20347 started on Friday, March 31st.

Work location: N. 6th St., between Cecil B. Moore St. and Diamond St.