Chelten / Maplewood

Current Phase:

Start:

Spring 2023

Completion:

Spring 2024

Map of project 20464 affected streets.

Overview

Project #20464 Chelten / Maplewood will replace water mains in the Germantown neighborhood in Northwest Philadelphia.

Streets Affected

  • Wayne Ave. from W. School House Ln. to W. Chelten Ave.
  • Maplewood Ave. from Greene St. to Wayne Ave.
  • W. Chelten Ave. from Germantown Ave. to Wayne Ave.
  • Heiskell St. from E. Armat St. to E. Chelten Ave.
  • Haines St. from Germantown Ave. to Dead End, south of McCallum St.
  • E. Price St. from Baynton St. to Morton St. (+ GSI Work)
  • Wayne Ave. from W. Coulter St. to W. School House Ln. (+ GSI Work)
For worksite issues, contact:
For more information, contact:

Project #20464

Project Type
ZIP Code
Council District

Project Files

20464 Construction LetterApril 21, 2023
Jump to Top