Manayunk, Northwest Philadelphia
Wilde / Leverington
Current Phase: Pre-Construction, NTP Issued
Start:
Estimated April 2023
Completion:
Estimated January 2024
Overview
Project #20649 Wilde / Leverington will replace water mains in the Manayunk neighborhood in Northwest Philadelphia.
Streets Affected
- Wilde St. from Krams St. to Green Ln.
- Leverington Ave. from Main St. to Silverwood St.
- Ripka St. from Umbria St. to Wilde St.
- St. Davids St. from Dupont St. to Green Ln.
- Carson St. from Main St. to Cresson St.
- Carson St. from St. Davids St. to Silverwood St.
- Gay St. from Cresson St. to Silverwood St.