Kinsey / Cloud

Current Phase:

Start:

Estimated February 2025

Completion:

Estimated Summer 2025

Overview

Project #40775 Kinsey / Cloud will replace water and sewer mains infrastructure in the Frankford neighborhood. Work is estimated to start in 2025.

The map above shows where new water mains will be installed and the service lines connected to the new mains. These properties may experience limited water interruptions during construction.

An assigned PWD inspector and engineer will be on-site and can answer questions about the work. Inspector and engineer contact information will be listed below when construction is nearing.

Streets Affected

  • Cloud St. from Waln St. to Church St.
  • Kinsey St. from Frankford Ave. to Torresdale Ave.
For worksite issues, contact:
For more information, contact:

Project #40775

Project Type
ZIP Code
Council District

Project Files

#40775 Construction LetterJanuary 31, 2025