Oxford / Hope

Skip to Updates ↓

Current Phase:

Start:

March 2022

Completion:

Estimated May 2023

Overview

Project #40851 Oxford / Hope will replace water mains and sewer pipes in the Olde Kensington neighborhood.

Streets Affected

  • Hope St. from W. Palmer St. to Cecil B. Moore Ave.
  • W. Oxford St. from N. Howard St. to Frankford Ave.
  • N. Howard St. from W. Oxford St. to Jefferson St.
  • Jefferson St. from Mascher St. to N. Front St.
  • Jefferson St. from N. Front St. to Frankford Ave. (includes Sewer Lining work)
For worksite issues, contact:
For more information, contact:

Project #40851

Project Type
ZIP Code
Council District

Project Files

40851 Construction LetterMarch 11, 2022

Updates

Updated construction timeline

The current estimated completion of the Jefferson St. component of this project is the end of March 2023.

The current estimated completion of the entire project is mid May 2023.

Posted by:
Amy Hopf
Category:
Project Update

Water service interruption

Jefferson St. between Hope St. & N. Howard St., will have a water shut-off with water service interrupted on 11/28 and/or 11/29.

Those affected will be notified 24hrs in advance, at the latest, for each individual shutdown.

Jump to Top