Carroll Park, West Philadelphia
SAP5 Priority Reconstruction Work
Overview
Project #41194 SAP5 Priority Reconstruction Work is a planned PWD project in West Philadelphia. It will build new water mains and sewers.
An assigned PWD inspector and engineer will be on-site and can answer questions about the work. Construction contact information, timelines, and streets affected will be listed here when construction is nearing.
For more information, please email the PWD community outreach team at water.projects@phila.gov. Please specify the project name, project number, and ZIP code in your email.
Streets Affected
| Street | Segment | Type of Work |
|---|---|---|
| W Thompson St. | from N 59th St to to N 60th St. | New Water Main, New Sewer |
| N 57th St. | from W Girard Ave. to W Thompson St. | New Water Main, New Sewer |
| N Redfield St. | from W Girard Ave. to W Thompson St. | New Water Main, New Sewer |
| N Redfield St. | from W Thompson St. to Master St. | New Sewer |
For worksite issues, contact:
- Gary Seifert
Division Engineer
Gary.J.Seifert@phila.gov
215-685-6363
For more information, contact:
- PWD Community Outreach Team
water.projects@phila.gov