22nd Street

Skip to Updates ↓

Current Phase:

Start:

November 2023

Completion:

Estimated Early April 2024

Overview

This project will replace water mains and sewer pipes along S. 22nd St. between Locust St. to Walnut St in Fitler Square.

Streets Affected

  • S. 22nd St. from Locust St. to Walnut St.
For worksite issues, contact:
For more information, contact:

Project #41215

Project Type
ZIP Code
Council District

Updates

Construction Update: March 2024

Due to unforeseen circumstances, Project #41215 is now estimated to be complete by early April 2024.

Posted by:
Amy Hopf
Category:
Project Update

Construction Update: Mid-December 2023

As of mid-December, work to replace the water main along S 22nd is about 75% complete and is estimated to be complete by mid-January 2024.

The sewer work will begin immediately after and is scheduled to take 5 weeks to complete. Re-paving will follow the sewer work.

With no unanticipated delays, the project will be complete by late February 2024.

Posted by:
Amy Hopf
Category:
Project Update

Construction started for project #41215

Carusone Construction began work for project #41215 on Tuesday, 11/7/23.
22nd Street from Locust to Walnut will be fully closed during working hours and reopened at the end of each day.