Cedar Park 2

Skip to Updates ↓

Current Phase:

Start:

November 2023

Completion:

Spring 2024

Overview

Project #50168 (Cedar Park 2) will implement green infrastructure to improve the stormwater management of the Cedar Park neighborhood in West Philadelphi.

This is part of the overall Green Infrastructure Initiative implemented by City of Philadelphia called Green City, Clean Waters.

There are two GSI projects in Cedar Park as part of this initiative:

Streets Affected

  • S. 52nd St. from Baltimore Ave. to Willows Ave.
  • Whitby Ave. from S. 53rd St. to Baltimore Ave.
  • Willows Ave. from S. 52nd St. to S. 51st St.
  • Pentridge St. from S. 52nd St. to S. 51st St.
  • S. 50th St. from Pentridge St. to Florence Ave.
For worksite issues, contact:
For more information, contact:

Project #50168

Project Type
ZIP Code
Council District

Project Files

50168 Construction LetterJuly 25, 2023

Updates

Project Schedule for #50168: Updated January 2024

Tentative Project Schedule for #50168:

    • Willows Ave. from S. 52nd St. to S. 51st St. completed in November/December 2023
    • S. 50th St. from Pentridge St. to Florence Ave. – completed in December 2023/January 2024
    • Pentridge St. from S. 52nd St. to S. 51st St. – to be completed in January/February 2024
    • Whitby Ave. from S. 53rd St. to Baltimore Ave. – to be completed in February/March 2024
    • S. 52nd St. from Baltimore Ave. to Willows Ave. – to be completed in March/April 2024