Wayne & Manheim

Skip to Updates ↓

Current Phase:

Start:

October 2019

Completion:

December 2020

Overview

Project #50177 (Wayne & Manheim) will implement green infrastructure to improve the stormwater management of the Germantown neighborhood. This is part of the Green Stormwater Infrastructure Initiative called Green City, Clean Waters.

Streets Affected

  • Wayne Ave. from W. Penn St. to Hansberry St.
  • Hansberry St. from Wayne Ave. to Henley St.
  • Manheim St. from Morris St. to Pulaski Ave.
  • Newhall St. from Manheim St. to Seymour St.
  • Seymour St. from Morris St. to Pulaski Ave.
  • Knox St. from W. Queen Lane to Hansberry St.
  • Manheim St. from Pulaski Ave. to Newhall St
  • Ashmead Place from Greene St. to Germantown Ave.
  • W. Queen Lane from Greene St. to Germantown Ave.
For worksite issues, contact:
For more information, contact:

Project #50177

Project Type
Green Tools
ZIP Code
Council District

Project Files

50177 Project FactsheetNovember 5, 2020 50177 Pre-Construction LetterNovember 5, 2020

Updates

Construction substantially complete

Construction substantially complete with all green stormwater infrastructure systems installed. Green tools will be planted in spring 2021.

Posted by:
Amy Hopf
Category:
Project Update

Construction began

Posted by:
Amy Hopf
Category:
Project Update

Construction (NTP) letter sent to residents

Letter sent to impacted streets and surrounding area – roughly 430 homes.