Current Phase:

Start:

March 2023

Completion:

Estimated Mid 2025

Overview

Project #50199 Lancaster Avenue 2 will implement green stormwater management infrastructure tools in the Mantua/Haverford North neighborhoods in West Philadelphia.

This project is part of the Green City, Clean Waters program. There will be a series of projects in the area:

Streets Affected

Street Segment Type of Work
Fairmount Ave. from N. 44th St. to N. 43rd St.
Wallace St. from N. 44th St. to N. 43rd St.
N. 44th St. from Haverford Ave. to Wallace St.
Haverford Ave. from N. 42nd St. to Brooklyn St.
Brooklyn St. from Haverford Ave. to Wallace St.
N. 42nd St. from Haverford Ave. to Wallace St.
Wallace St. from Brooklyn St. to N. 43rd St.
For worksite issues, contact:
For more information, contact:

Project #50199

Project Type
Watershed
ZIP Code
Council District

Project Files

#50199 Construction LetterFebruary 28, 2023 Lancaster Area GSI MapJanuary 24, 2022

Updates

Construction began

Construction for Project #50199 began on Monday, March 13, 2023. Work began on N. 42nd St. between Haverford Ave. and Wallace St.