Feltonville, North Philadelphia
Feltonville Rec Center
Current Phase: Pre-Construction, NTP Issued
Start:
Estimated Summer 2023
Completion:
Estimated Spring 2024
Overview
Project #50266 Feltonville Rec Center will implement green stormwater management infrastructure tools in the Feltonville neighborhood.
This is part of the overall Green Infrastructure Initiative implemented by City of Philadelphia called Green City, Clean Waters.
Streets Affected
- A St. from E. Wyoming Ave. to E. Mentor St.
- Ella St. from E. Wyoming Ave. to E. Mentor St.
- E. Loudon St. from A St. to Ella St.
- B St. from E. Wyoming Ave. to E. Loudon St.
For worksite issues, contact:
- Frank Stollenwerk
Project Engineer
Francis.Stollenwerk@phila.gov
215-964-8036
For more information, contact:
- Amy Hopf
PWD Construction Liaison
amy.hopf@phila.gov