Tarken Streets 1

Current Phase:

Estimated Start:

Late Summer 2026

Estimated Completion:

Fall 2027

Overview

Project #50352 Tarken Streets 1 will build new water mains and implement green stormwater management infrastructure tools in the Oxford Circle neighborhood in Northeast Philadelphia.

This is part of the overall Green Infrastructure Initiative implemented by City of Philadelphia called Green City, Clean Waters.

For more information, please email the PWD community outreach team at water.projects@phila.gov. Please specify the project name, project number, and ZIP code in your email.

Streets Affected

Street Segment Type of Work
Summerdale Ave. from Devereaux Ave. to Oxford Ave.Tree Trench
Benner St. from Summerdale Ave. to Augusta St.New Water Main
Benner St. from Augusta St. to Frontenac St.New Water Main, Tree Trench
Benner St. from Frontenac St. to Belden St.New Water Main, Bumpout, Tree Trench
Benner St. from Belden St. to Loretto Ave.Bumpout, Tree Trench
Benner St. from Loretto Ave. to Alma St.Subsurface Trench
Frontenac St. from Comly St. to Benner St.New Water Main
For worksite issues, contact:
For more information, contact:

Project Files

Project #50352 Construction LetterAugust 5, 2026 Project #50352 Pre-Construction Letter: April 2026May 5, 2026