Construction started for project #20525 along Jefferson St. between N. 12th St. and Broad St. Work began on 11/13/23 and is expected to be complete in Fall 2024.

Tentative schedule:

  • Master St from 13th to 16th: Jan & Feb 2024
  • Thompson St from 15th to 17th: March & April 2024
  • Broad St, Carlisle St, and Burns St: to follow