Update, as of February 12, 2024:

  • All water mains installed
  • 100 block of Cheltenham Ave – service line connections done today, 2/12
    • All other service connections complete
  • Tie-in at Tacony Crossing Apts will be done in March
  • Last steps:
    • Street restoration of Crescentville from Hammond to Cheltenham
    • Street restoration of Cheltenham from Crescentville to 7 Oaks
    • Sidewalk restoration – 100 block of Cheltenham
    • Disturbed grassy areas will receive soil and seed

Contractors anticipate 1-2 months to complete project (weather & external factors permitting)