Construction Update
Update, as of February 12, 2024:
- All water mains installed
- 100 block of Cheltenham Ave – service line connections done today, 2/12
- All other service connections complete
- Tie-in at Tacony Crossing Apts will be done in March
- Last steps:
- Street restoration of Crescentville from Hammond to Cheltenham
- Street restoration of Cheltenham from Crescentville to 7 Oaks
- Sidewalk restoration – 100 block of Cheltenham
- Disturbed grassy areas will receive soil and seed
Contractors anticipate 1-2 months to complete project (weather & external factors permitting)