Water main replacement work began in late March 2024, starting on the southwest end of Fairmount Ave. As of April 2, 2024, work has reached the intersection where Fairmount Ave., N. Preston St., and Olive St. meet.

Green stormwater infrastructure (GSI) work has also started on Fairmount Ave.