Completed Work: All water main work is complete.

  • S. 12th St. from Porter St. to Wolf St.
  • Camac St. from Oregon Ave. to Shunk St.
  • Iseminger St. from Oregon Ave. to Shunk St.
  • Shunk St. from S. 12th St. to S. Broad St.

Active/Remaining Construction: 

  • Streets scheduled for repaving:
    • Moyamensing Ave. from Porter St. to Shunk St.

Road Closures/New Information

  • The “No Parking” signs on Porter from 13th to Broad: private plumber; not related to PWD work