Friday, August 29: Project #41102 Update
Completed Work:
- S. Clarion St. from Shunk St. to Ritner St.
- S. Juniper St. from Shunk St. to Ritner St.
- S. Camac St. from Porter St. to Ritner St.
Active/Remaining Construction:
- S. Sartain St. from W. Moyamensing Ave. to Ritner St.
- Repaving of disturbed area to be done by October 2025
- S. Alder St. from Porter St. to Ritner St.
- Active construction
- S. 11th St. from Porter St. to Ritner St.
- S. Iseminger St. from Porter St. to Ritner St.
Road Closures/New Information
- The “No Parking” signs on Porter from 13th to Broad: private plumber; not related to PWD work