Order of work for Project #50176
Construction of new water mains along Wolf Street will start in October 2024. All water main work will be done before green stormwater infrastructure systems are built.
GSI work will begin in December 2024.
Construction of new water mains along Wolf Street will start in October 2024. All water main work will be done before green stormwater infrastructure systems are built.