Tentative Project Schedule for #50168:

    • Willows Ave. from S. 52nd St. to S. 51st St. completed in November/December 2023
    • S. 50th St. from Pentridge St. to Florence Ave. – completed in December 2023/January 2024
    • Pentridge St. from S. 52nd St. to S. 51st St. – to be completed in January/February 2024
    • Whitby Ave. from S. 53rd St. to Baltimore Ave. – to be completed in February/March 2024
    • S. 52nd St. from Baltimore Ave. to Willows Ave. – to be completed in March/April 2024