,

Girard Estates Green Streets

Skip to Updates ↓

Current Phase:

Start:

Estimated Early 2025

Completion:

Estimated October 2025

Overview

Project #50176 Girard Estates Green Streets will implement green stormwater management infrastructure tools in the Girard Estates neighborhood in South Philadelphia.

The project will also install new water mains on Wolf St. from S. 19th St. to Woodstock St.

This project is part of the Green City, Clean Waters 25-year plan.

Streets Affected

  • Wolf St. from S. 19th St. to Woodstock St. (Water Main Replacement)
  • Wolf St. from S. 19th St. to Passyunk Ave.
  • S. 18th St. from W. Ritner St. to Wolf St.
  • S. 19th St. from W. Ritner St. to Wolf St.
  • S. 20th St. from W. Ritner St. to Durfor St.
  • W. Ritner St. from S. 20th St. to S. 21st St.
  • W. Porter St. from S. Garnet St. to S. 21st St.
For worksite issues, contact:
For more information, contact:

Project #50176

Project Type
Green Tools
Watershed
ZIP Code

Project Files

#50176 Construction LetterOctober 3, 2024 50176 Project SummaryOctober 3, 2024

Updates

Order of work for Project #50176

Construction of new water mains along Wolf Street will start in October 2024. All water main work will be done before green stormwater infrastructure systems are built.

GSI work will begin in December 2024.

Posted by:
Amy Hopf
Category:
Project Update

GENA Community Meeting

Danielle Stollak and Amy Hopf attend Girard Estates Neighbors Association (GENA) January community meeting to share information about project.

Jump to Top