Howard / Orianna

Skip to Updates ↓

Current Phase:

Start:

Summer 2025

Completion:

Estimated Fall 2026

Overview

Project #41018 Howard / Orianna will replace water and sewer mains along streets in the Norris Square neighborhood in North Philadelphia.

Work is estimated to start in Late 2025/Early 2026.

An assigned PWD inspector and engineer will be on-site and can answer questions about the work. Construction contact information, timelines, and streets affected will be listed here when construction is nearing.

Streets Affected

Street Segment Type of Work
N. Leithgow St. from W. Norris St. to Diamond St.New Water Main & Sewer
N. 2nd St. from W. Dauphin St. to W. York St. New Water Main & Sewer
N. Orianna St. from W. Dauphin St. to W. York St. New Water Main & Sewer
N. Howard St. from W. Susquehanna Ave. to W. Dauphin St.New Water Main
N. Hancock St. from Diamond St. to W. Susquehanna Ave.New Water Main
Palenthorp St. from Diamond St. to W. Susquehanna Ave.New Water Main
For worksite issues, contact:
For more information, contact:

Project Files

#41018 Construction LetterOctober 6, 2025

Updates

Construction Update for Project #41018: October 2025

In October 2025, these blocks have received new water mains:

  1. N. Leithgow St. from Susquehanna Ave. to Diamond St.
  2. N. Howard St. from W. Susquehanna Ave. to W. Dauphin St.
  3. N. Hancock St. from Diamond St. to W. Susquehanna Ave.

Active construction is expected in the area until Fall 2026.