64th Street Corridor

Current Phase:

Start:

March 2024

Completed:

Fall 2025

Overview

Project #50220 64th Street Corridor is a Water Department capital project that implemented green stormwater management infrastructure tools in the Overbrook neighborhood in West Philadelphia.

This project is part of the Green City, Clean Waters program. It is part of several GSI projects in a multi-year Morris Park neighborhood package.

For more information, please email the PWD community outreach team at water.projects@phila.gov. Please specify the project name, project number, and ZIP code in your email.

Streets Affected

Street Segment Type of Work
N. 64th St. from City Ave. to Woodbine Ave.
N. 64th St. from Woodcrest Ave. to Malvern Ave.
Sherwood Rd. from N. 64th St. to Lancaster Ave.
Drexel Rd. from N. 64th St. to Lancaster Ave.
For worksite issues, contact:
For more information, contact:

Project Files

#50220 Construction LetterFebruary 28, 2023 50220_Project SummaryNovember 15, 2022