Protestant Home and Devereaux

Skip to Updates ↓

Current Phase:

Start:

September 2023

Completion:

Estimated Summer 2024

Overview

Project #50090 Protestant Home and Devereaux will implement green stormwater management infrastructure tools in the Lawndale/Oxford Circle neighborhoods in Northeast Philadelphia.

This project is part of the Green City, Clean Waters 25-year plan.  It is part of several GSI projects in a multi-year Lawncrest project package.

Streets Affected

Street Segment Type of Work
Magee Ave. from Tabor Ave. to Montour St.
Levick St. from Martins Mill Rd. to Montour St.
Martins Mill Rd. from Lawndale Ave. to Tabor Ave.
Algon Ave. from Oxford Ave. to Devereaux Ave.
Devereaux Ave. from Algon Ave. to Summerdale Ave.
For worksite issues, contact:
For more information, contact:

Project #50090

Project Type
ZIP Code

Project Files

Lawncrest Neighborhood MapJuly 14, 2023 #50090 Construction LetterMarch 22, 2023 50090 Bid Award Letter and MapDecember 29, 2022

Updates

Construction update: Nearing 50% complete

For project #50090, 3 systems have been completed. The remaining 5 systems are expected to be completed by the end of May 2024.

Posted by:
Amy Hopf
Category:
Project Update

Construction began

Construction for project #50090 started on September 25, 2023.

Jump to Top