Lawncrest Streets North

Skip to Updates ↓

Current Phase:

Start:

July 2020

Completion:

Spring 2021

Overview

Project #50217 (Lawncrest Streets North) will implement green infrastructure to improve the stormwater management of the Lawncrest neighborhood. This is part of the overall Green Infrastructure Initiative implemented by City of Philadelphia called Green City, Clean Waters.

It is part of several GSI projects in a multi-year Lawncrest project package.

Streets Affected

  • Bingham St. from Van Kirk St. to Comly St.
  • Elsinore St. from Van Kirk St. to Comly St.
  • Palmetto St. from Van Kirk St. to Comly St.
  • Malta St. from Van Kirk St. to Comly St.
  • Comly St. from Bennington St. to Colgate St.
  • Colgate St. from Comly St. to Benner St.
  • Lawndale St. from Comly St. to Benner St.
  • Van Kirk St. from Rising Sun Ave. to Malta St.
For worksite issues, contact:
For more information, contact:

Project #50217

Project Type
ZIP Codes
Council District

Project Files

Lawncrest Neighborhood MapJuly 14, 2023 50217 Pre-Construction LetterOctober 27, 2020

Updates

Construction Complete

Construction for project #50217 was completed in April 2021.

Posted by:
Amy Hopf
Category:
Project Update

Construction update: work 50% complete

Posted by:
Amy Hopf
Category:
Project Update

Construction began

Pre-con meeting took place 6/10/2020, attendees: Amy Hopf, Julia Morris, Jamie Williams – inspector, Nick DelCasale – project engineer, rep from Donato Spaventa & Sons (contractor).
Estimated end date will be around May 2021.

Posted by:
Amy Hopf
Category:
Project Update

Construction (NTP) letter sent to residents

Sent to 600 residents.
50217_PreConstructionNTP_Letter

Posted by:
Amy Hopf
Category:
Project Update

Bid letter sent to residents

Bid letter sent to 600 residents.
50217_BidAward_Letter