,

Conestoga Green Streets

Skip to Updates ↓

Current Phase:

Start:

February 2024

Completion:

Estimated November 2024

Overview

Project #50296 Conestoga Green Streets will implement green stormwater management infrastructure tools in the Hestonville/Overbrook neighborhood of West Philadelphia.

This is part of the overall Green Infrastructure Initiative implemented by City of Philadelphia called Green City, Clean Waters.

Streets Affected

  • Media St. from N. Conestoga St. to N. 55th St.
  • Media St. from N. Peach St. to N. 54th St.
  • Bible Way from Lancaster Ave. to N. 52nd St.
  • N. 51st St. from Warren St. to Master St.
  • Master St. from Lancaster Ave. to N. 50th St.
  • Warren St. from N. 52nd St. to N. 53rd St. (+ New Water Mains)
For worksite issues, contact:
For more information, contact:

Project #50296

Project Type
Green Tools
ZIP Code

Project Files

50296 Construction LetterNovember 8, 2023

Updates

19th Police District Town Hall meeting: Mon, Jan 22

The Philadelphia Water Department will be joining the 19th Police District Town Hall meeting on Monday, January 22nd,2024 at 6pm.

Updates about green stormwater infrastructure (GSI) projects in the Overbrook Park/Haddington neighborhoods of West Philly that are in design or in construction will be reviewed.

Meeting Information: 

  • Date & Time: Monday, January 22nd, 2024 at 6:00pm
  • Location: 19th Police District located at 6059 Haverford Ave, 19151

Projects Covered:

In Construction

 

In Design

 

Jump to Top