Final Inspection Request

A final inspection of all stormwater projects must be conducted by PWD to verify all stormwater components and site features have been installed in accordance with the approved plans and are functioning properly.

The initial final inspection for all sites must be requested via this form. Any follow-up inspections can be scheduled directly with the assigned inspector.

Should follow format: FY##-XXXX-####-0#, where # represents digits, X represents letters, and other characters are literal. (Will also accept older tracking numbers with the format ####-####-##.)

Verify that the prerequisites listed below have been completed:

The applicant is advised to review Appendix M. PCSMP Project Closeout in the Stormwater Management Guidance Manual regarding how to complete the project closeout process.

These items will be reviewed by PWD and incorporated as feedback into the Post-Construction Stormwater Management (PCSM) Final Inspection Report.

The items noted above will be checked before the final inspection is scheduled. Incomplete items will result in a delayed final inspection.

During the final inspection, PWD will need access to the interiors of manholes, outlet structures, cleanouts, and observation wells. Applicants must have the necessary personnel and tools available to open structures. Representatives from the contractor responsible for the construction and ownership are required to attend.

Please provide three different dates, at least 7 days from the date this form is submitted, and the times on each of those dates (between 8am and 4pm), available for the final inspection.

1
2
3
1

Provide at least one email address to receive a confirmation email, and to contact in case of questions or issues with your request.