# | Each plan sheet submitted to PWD must be legible and include the following items: |
---|---|
1 | Project name |
2 | PWD project tracking number |
3 | Revision date(s) |
4 | Title of plan sheet |
5 | Signature and seal of Registered Professional (dated) for Final Construction Drawings |
6 | Plan scale including measurable scale bar (1” = 10’, 20’, 30’, 40’, 50’, 60’, or 100’) (50’ or less for Record Drawings) |
7 | North arrow |
8 | Legend that clearly shows all symbols, line types, and hatchings used on the plan |
9 | All proposed changes or additions to existing conditions should be represented on the plan in a line weight heavier than that used for existing conditions |
10 | Street lines, street names, rights-of-way, and easements |