Table E-6: Standard Sequence of Construction Notes

  Print / Download
#Note
1At least seven (7) days prior to any earth disturbance, the Inspections Coordinator of PWD (Office: 215-685-6387) must be called to schedule a preconstruction meeting.
2At least three (3) days prior to (applicant to name each SMP) installation, the Inspections Coordinator of PWD (Office: 215-685-6387) must be called to schedule an inspection (for each SMP).
3All stone that makes up the (applicant to name each infiltration SMP) must remain free of sediment. If sediment enters the stone, the contractor may be required to remove the sediment and replace it with clean-washed stone.
4Upon completion of all earth disturbance activities and permanent stabilization of all disturbed areas, the owner and/or operator shall contact Inspections Coordinator of PWD (Office: 215-685-6387) for a final inspection prior to removal/conversion of the E&S BMPs.
5As soon as slopes, channels, ditches, and other disturbed areas reach final grade, they must be stabilized. Cessation of activity for four (4) days or longer requires temporary stabilization.
6The NPDES Notice of Termination (N.O.T.) must be submitted to PA DEP upon completion of construction (when applicable).
7Water pumped from work areas should be treated for sediment removal prior to discharging to a “surface water” (when applicable).