Appendices

Table E-4: Erosion and Sediment Control Plan Requirements

  Print / Download
#Requirement
1General plan presentation requirements listed in Table E‑1
2Name of owner and designer
3Site address (existing and proposed, if different)
4Location map including site location within watershed(s)
5Property lines, subdivision or lot consolidation lines, all metes, bounds, boundaries, dimensions, building lines and setbacks (if two or more lines (property lines, limits of disturbance (LOD) lines, right-of-way line, etc.) coincide at the same location or over one another on the plan, separate them on additional plan sheets)
6Street lines, street names, lot names, easements, other land divisions, and their purposes and confirmed locations
7Location of boundaries of all existing and proposed rights-of-way, easements, cartway widths for all streets and private roads, and drainage rights-of-way to remain post-construction (any proposed changes to the City plan should also be noted with an ordinance number, if known)
8Location/outline of all existing structures to remain within 25 feet of the limit of disturbance
9Location of all existing utilities (water, sewer, stormwater), including stormwater management practices, to remain above and below ground within 25 feet of the limit of disturbance
10Existing topography of site (contours, sub-basins, etc.) in one-foot contour intervals (minimum) on-site and on adjacent lands within 25 feet of the property line and on the full width of abutting public lands, and private rights-of-way and easement(s)
11Location of all right-of-way encroachments, such as egress wells, stairs, light poles, trees, building overhangs, etc.
12Delineation, labeling, and square footage of the proposed LOD, including all utility connections, sidewalk replacement, stockpiles, and construction entrances within the LOD. The LOD should not only take into consideration proposed improvements, but also areas likely to be disturbed during construction, such as for the installation of erosion and sediment control measures.
13Proposed topography of site (distinguish between existing and proposed contours) in one-foot contour intervals (minimum)
14Identification of all proposed site improvements, such as buildings, basements, parking lots, driveways, landscaping, SMPs, drainage, etc., that should be distinguished from any existing features to remain
15Location and dimensions of all existing and proposed driveways, curb cuts, and off-street parking lots, with distances from lot lines
16Proposed building lines with street setback lines and distances to other existing and proposed buildings if within 15 feet
17Proposed lot lines and lot identification numbers, dimensions, and areas
18Delineation of impervious surfaces
19Location of vegetation identified for preservation and planned landscape areas
20Location of all proposed water and fire utility connections, including proposed sizes, if known Water meter/meter pit must be shown within 35 feet of the property/house/right-of-way line (show dimension from property line to metered structure) Include backflow prevention on the water line, when applicable
Location of all proposed sanitary sewer and stormwater connections including proposed sizes, if known (sewer connections made directly into inlets and manholes are not permitted)
22Extent and boundaries of 100-year floodplain in relation to the project
23Depiction of post-development hydrology of the site with flow lines and/or drainage areas including discharge points from property and type of discharge (diffused, concentrated, piped, etc.)
24Location of any proposed on-site disposal systems (septic tanks) and drain fields
25Location of all proposed erosion and sediment control measures, including, but not limited to, inlet protection, silt fence and/or compost filter sock, rock filter outlet, rock construction entrance, pumped water filter bag, concrete washout station, and stockpiles, which must be surrounded by silt fencing
26Dimensions of rock construction entrance(s), which must be, at minimum, 50 feet in length and 20 feet in width
27Tree protection fencing around existing trees proposed to remain
28Geotextile or filter stone for erosion protection of soil beneath any proposed riprap
29Objects of considerable mass (i.e. concrete blocks, sand bags, etc.) immediately downslope of any compost socks placed on paved surfaces (at same intervals as recommended by sock manufacturer for stakes)
30The designer must prescribe dust control measures that are appropriate to the project. The designer is referred to the City of Philadelphia Department of Public Health Air Management Services Construction/Demolition/Earthworks Dust Control Requirements FAQ for guidance.
31Standard construction details from the PA DEP Erosion and Sediment Pollution Control Manual (2012 or latest) for inlet protection, silt fence and/or compost filter sock, rock filter outlet, rock construction entrance, pumped water filter bag, concrete washout station, and stockpile location (if any of these erosion and sediment control measures do not apply to the project site, justification must be provided as notes on the plan)
32Standard Erosion and Sediment Control Notes listed in Table E‑5, as applicable
33Standard Sequence of Construction Notes listed in Table E‑6, as applicable
34Electronic signature and seal of a licensed professional if project’s limit of disturbance exceeds 15,000 square feet