#Requirement
1General plan presentation requirements listed in Table E‑1 (The preparer of the Record Drawing(s) must prominently display their signature and professional seal, or, in the case of Licensed Contractors, their signature, printed name, business title, company name, and City of Philadelphia Department of Licenses and Inspections Contractor License Number, all of which must be clearly labeled, on each Record Drawing plan sheet.)
2Labeling on each document as “Project Record” with large, red letters
3Record Drawing drafting date on each sheet
4Drawing scale of 1”=50’ or less
5Information confirmed to be in accordance with the Approved Post‑Construction Stormwater Management Plan (PCSMP) highlighted in yellow
6Information that deviates from the Approved PCSMP highlighted in red
7Benchmark elevation, description, and location on each plan sheet
8Horizontal variations greater than one foot shown dimensionally or through stations
9Vertical elevation variations greater than 0.1 feet shown for all design elevations shown
10Locations of all proposed stormwater management practices (SMPs) in plan view
11Distance from lot lines to the constructed SMPs
12Locations of utilities
13Spot grade elevations and/or contour lines at one-foot intervals
14Stormwater flow direction arrows
15Elevations across dam embankments
16Elevations at the top of risers
17Elevations at the invert and rim of all orifice openings in risers and control structures
18Elevations across emergency spillways
19Elevations across the bottom of ponds (excluding wet ponds)
20Elevations for of all inlet and outlet controls
21Elevations at inverts of all pipes, swales, and drains
22Measurements and invert elevations for all orifices, weirs, and other flow control devices
23Pipe and culvert material, length, size, and slope, inlet and outlet locations, and rim and invert elevations
24Information for any energy dissipation measures
25Drainage areas for each SMP, if they differ from the Approved PCSMP
26Detail or cross-section of each SMP with all pertinent elevations labeled