Chapter 3 Site Design and Stormwater Management Integration

3.4 How To Show Compliance

  Print / Download

Section 3.4 provides detail on how to ensure and demonstrate that stormwater management design strategies are implemented in accordance with the Philadelphia Water Department’s (PWD’s) Stormwater Regulations (Stormwater Regulations). This Section provides resources that can be used in conjunction with the design requirements detailed in Section 3.2 and Chapter 4.

Section 3.4.1 gives specific guidance and requirements for compliance with the following:

  • Water Quality requirement,
  • Channel Protection requirement,
  • Flood Control requirement, and
  • Public Health and Safety Release Rate requirement.

Compliance with some Stormwater Regulations may not be required for all projects; therefore, the applicant is referred to Chapter 1 to assess and/or confirm applicability of specific requirements.

Section 3.4.2 provides guidance and requirements for the design of storm sewer systems.

Section 3.4.3 contains calculation methods and design tools to assist in stormwater management design.

3.4.1 Regulatory Compliance Documentation Requirements

After determining which Stormwater Regulations are applicable to the project site using Chapter 1, the applicant can use this Section as a guide to document regulatory compliance within the Post‑Construction Stormwater Management Plan (PCSMP) Review Phase. For each requirement, a step-by-step guide to documenting compliance is provided. While some steps are either identical or similar between requirements, this redundancy is provided for projects where not all requirements are applicable. The applicant is referred to Section 2.3.1 for complete PCSMP Review Phase submission requirements.

Water Quality

The designer must use the following steps to document compliance with the Water Quality requirement. This requirement, with key differences noted below and in Section 1.3, contains the design standards for Stormwater Retrofit projects. No other Post‑Construction Stormwater Management Requirement is applicable to voluntary stormwater management.

Step 1:

Delineate all post-development impervious area within the project limit of disturbance (LOD) and differentiate between disconnected impervious cover (DIC) and directly connected impervious area (DCIA). For projects located in combined sewer areas, also differentiate between DCIA that meets roof runoff isolation requirements (Section 3.1.7) and all other DCIA. For Stormwater Retrofit projects, delineate the impervious area draining to any proposed stormwater management practices (SMPs). The roof runoff isolation pollutant-reducing practice does not apply for Stormwater Retrofit projects.

Step 2:

For all DIC within the project LOD, identify the proposed DIC strategy (i.e., rooftop disconnection, pavement disconnection, tree disconnection credit, green roof, or porous pavement).

DIC strategies must meet applicable requirements in Section 3.1.5. For Stormwater Retrofit projects, different policies on DIC strategies apply. Refer to Section 1.3 for more information on incorporating DIC into Stormwater Retrofit projects.

Step 3:

Delineate drainage areas and footprints for each proposed SMP or series of SMPs if they share the same drainage area) and all DCIA within each drainage area. Check to ensure maximum loading ratio requirements can be met for each proposed SMP. Loading ratio requirements are discussed in Section 3.2.6.

Step 4:

Calculate the Water Quality Volume (WQv) for each proposed SMP (or series of SMPs, if applicable) using the following equation:

Where:

WQv = Water Quality Volume [cubic feet]
DCIA = Directly Connected Impervious Area [square feet]
R = 1.5 inches runoff depth

Step 5:

Determine the sewershed of the discharge point of each proposed SMP.

Design SMP(s) to provide management of the WQv and to meet all SMP design requirements by SMP-type in Chapter 4. WQv management requirements differ by infiltration feasibility and sewershed, as detailed in Chapter 1, and based on these factors, proceed to Step 5a, Step 5b, or Step 5c.

Step 5a:

Where infiltration is feasible:

  • Design SMP(s) to infiltrate 100% of WQv.
  • Size SMP(s) to provide static storage of the WQv below the lowest outlet elevation.
  • Bioinfiltration SMPs can be designed for an adjusted WQv= (DCIA) [sf] x (1-inch runoff depth/12) if the designer demonstrates through modeling that the full WQv can be routed dynamically through the system. See Section 4.1 for more information.  
  • Design SMP(s) to ensure drain down time is no more than 72 hours based on the tested infiltration rate with an applied factor of safety of two to the geometric mean of the tested infiltration rates (design infiltration rate) and the SMP horizontal surface area (footprint).
Step 5b:

Where infiltration is not feasible and the project is located in a combined sewer area:

  • Design SMP(s) to route 100% of the WQv that is not infiltrated through an acceptable pollutant-reducing practice (Table 3.1‑3). This is not a requirement for Stormwater Retrofit projects.
  • Design SMP(s) to ensure a slow release rate on-site that does not exceed 0.05 cubic feet per second (cfs) per acre of DCIA when routing a 1.7-inch PWD Design Storm.
    See Section 3.4.3 for calculation methods and Table 3.4‑4 for dimensionless rainfall distribution for the PWD Design Storm. A curve number of 98 must be used for all DCIA when performing routing calculations for the Water Quality requirement.
  • Design SMP(s) to ensure drain down time is no more than 72 hours after the storm event for a 1.7-inch PWD Design Storm. The drain down time is the time required for evacuation of the instantaneous storage of the WQv in the SMP.
Step 5c:

Where infiltration is not feasible and the project is located in a separate sewer area or is a direct discharge project:

  • Design SMP(s) to route 100% of the WQv that is not infiltrated through an acceptable pollutant-reducing practice (Table 3.1‑3).
  • Design SMP(s) to ensure drain down time is no more than 72 hours after the 24-hour storm event. The drain down time is the time required for evacuation of the instantaneous storage of the WQv in the SMP.
Step 6:

For Development Projects only, when meeting the Water Quality requirement is not possible for all or a portion of the DCIA within the LOD, the applicant may propose payment of a one-time fee in lieu. The following must be documented for a fee in lieu request to be considered by PWD:

  • In the PCSMP Report, outline all stormwater management strategies that have been considered to comply with the Water Quality requirement, including off-site management as discussed in Section 3.2.4, and why they are not feasible or advisable.
  • Investigate and confirm that the Development Project proposal to pay fee in lieu will not adversely affect flooding, stream protection, neighboring properties, or be inconsistent with NPDES Permit requirements or any other applicable local, State, or Federal law.
  • On the PCSMP, identify the square footage, type, and location of DCIA that will not be managed in accordance with the the Water Quality requirement. This value will be used to calculate the one-time fee in lieu payment.

Complete PCSMP Review Phase submission requirements are provided in Section 2.3.1.

Channel Protection

The applicant must use the following steps to document compliance with the Channel Protection requirement, if applicable. The applicant is referred to Section 1.2.1 for details on Channel Protection exemptions.

Step 1:

Determine a point of analysis (POA) for the post-development condition. A POA is a common point of discharge from the project site or drainage area. A POA may serve one or several drainage areas and/or SMPs. PWD recommends using as few POAs as possible for compliance calculations. If there are multiple points of discharge from a property, it may still be possible to use a single POA if all discharge points lead to the same waterbody or outfall. Should a project fall in this category, contact PWD for more information as to how many POAs should be identified.

Step 2

Delineate drainage areas for each POA and all DCIA within each drainage area. All area within the project LOD must be accounted for within a POA, including areas that bypass SMPs.

Step 3

Design stormwater outlet controls (within or external to SMPs) to ensure the release rate at each POA does not exceed 0.24 cfs per acre of DCIA (draining to the POA) when routing a one-year National Resources Conservation Service (NRCS) Type II 24-hour design storm. The design precipitation depth of a one-year, 24-hour storm is 2.83 inches. See Section 3.4.3 for calculation methods, Table 3.4‑3 for design storm depths, and Table 3.4‑5 for dimensionless rainfall distribution for the NRCS Type II 24-hour design storm. Outlet controls and SMPs must also meet all design requirements of Chapter 4.

Where runoff is routed through an SMP prior to reaching a POA, design SMP(s) to ensure drain down time is no more than 72 hours after the storm event for a one-year NRCS Type II 24-hour design storm. The drain down time is the time required for evacuation of the instantaneous storage of the Channel Protection volume in the SMP.

All design information developed to document compliance with the Channel Protection requirement must be included in the PCSMP Review Phase Submission Package. This includes, but is not limited to:

  • PDF printout of completed Online Technical Worksheet;
  • Post-development drainage area plans; and
  • Flow routing calculations and model inputs and results for the one-year design storm.

Complete PCSMP Review Phase submission requirements are provided in Section 2.3.1.

Flood Control

The applicant must use the following steps to document compliance with the Flood Control requirement, if applicable. The applicant is referred to Section 1.2.1 for details on Flood Control exemptions.

Step 1:

Determine a POA for comparison of the predevelopment and post-development conditions. A POA is a common point of discharge from the project site or drainage area. A POA may serve one or several drainage areas and/or SMPs. PWD recommends using as few POAs as possible for compliance calculations. If there are multiple points of discharge from a property, it may still be possible to use a single POA if all discharge points lead to the same waterbody or outfall. Should a project fall in this category, contact PWD for more information as to how many POAs should be identified.

Step 2:

Determine the predevelopment and post-development drainage area(s) and drainage area conditions for each POA. The predevelopment condition is determined by the dominant land use for the ten years preceding the date of the project’s Existing Resources and Site Analysis (ERSA) Application submission. All area within the project LOD must be accounted for within a POA, including areas that bypass SMPs.

The applicant is referred to Table 3.4‑2 for acceptable curve numbers and must use the following guidance for determining land use designations for Flood Control:

  • Pervious area is considered to be area covered by a pervious surface that allows water to drain through it rather than running off of the site.
  • All non-forested pervious areas must be considered meadow in good condition for predevelopment runoff calculations.
  • Non-forested pervious area consists of the following cover types: meadow, grass/lawn, brush, gravel, dirt, porous pavements, and any combination of these cover types.
  • Dirt and gravel are generally considered to be pervious cover, however, if the applicant believes an impervious classification is more suitable, they can submit documentation, such as photographic evidence and testing results, to support this claim.
  • DIC should be represented as the appropriate cover type, as this management strategy does not apply to the Flood Control requirement; thus impervious area must be represented as impervious, green roof area as green roof, porous pavement area as porous pavement, and permeable paver area as permeable paver.
  • For redevelopment projects, in addition to any other pervious area, 20% of the existing impervious cover, when present, must be considered meadow (good condition) for the predevelopment runoff calculations.
Step 3:

Confirm or determine, if not done previously, the level of flood control required based on the project’s Flood Management District (Appendix D) and peak runoff rate requirements by Flood Management District, as per Table 3.4‑1 below.

If a project is located near or across a Flood Management District border, the applicant is responsible for contacting PWD to confirm the District requirements that apply to the project. In most cases, a project that is located in multiple Districts will be required to meet the requirements of the District within which each POA is located, resulting in discrete rate reductions for each POA.

Table 3.4‑1: Peak Runoff Rates for Management Districts
Step 4:

Design stormwater outlet controls (within, or external to, SMPs) to ensure the peak runoff rate in the proposed condition (left column of Table 3.4‑1) does not exceed the peak runoff rate in the predevelopment condition (right column of Table 3.4‑1) at each POA for the stated design storms. For a given Flood Management District, all storms’ rate reductions must be met concurrently. Peak rate reduction provided by SMPs that meet the Water Quality and Channel Protection requirements may be considered in sizing calculations for peak rate controls. See Section 3.4.3 for calculation methods, Table 3.4‑3 for design storm depths, and Table 3.4‑5 for dimensionless rainfall distribution for the NRCS Type II 24-hour design storm. Outlet controls and SMPs must also meet all design requirements of Chapter 4.

All design information developed to document compliance with the Flood Control requirement must be included in the PCSMP Review Phase Submission Package. This includes but is not limited to:

  • PDF printout of completed Online Technical Worksheet;
  • Predevelopment and post-development drainage area plans;
  • Predevelopment time of concentration (Tc) calculations;
  • Post-development Tc calculations (if demonstration of a Tc greater than an assumed six minutes is desired); and
  • Flow routing calculations and model inputs and results for predevelopment and post-development conditions during all design storms applicable to the Flood Management District’s required rate reductions.

Complete PCSMP Review Phase submission requirements are provided in Section 2.3.1.

Public Health and Safety Release Rate

The applicant must use the following steps to document compliance with a Public Health and Safety (PHS) Release Rate requirement, if applicable. The designer is referred to Section 1.2.1 for more information on the PHS Release Rate requirement.

Step 1:

Confirm the project-specific PHS Release Rate requirement with PWD Stormwater Plan Review. A PHS Release Rate requirement is stated as a peak runoff release rate in cfs per acre of earth disturbance, pervious and impervious, alike. This information will be noted by PWD during the Conceptual Review Phase (Section 2.3).

Step 2:

Determine a POA for the post-development condition. A POA is a common point of discharge from the project site or drainage area. A POA may serve one or several drainage areas and/or SMPs. Multiple POAs must be identified for project sites with multiple points of discharge.

Step 3:

Delineate drainage areas for each POA, the extent of earth disturbance within each drainage area, and the post-development condition within the LOD. All area within the project LOD must be accounted for within a POA, including areas that bypass SMPs.

Step 4:

Design stormwater outlet controls (within, or external to, SMPs) to ensure the peak runoff release rate at each POA does not exceed the project-specific PHS Release Rate requirement (cfs per acre LOD within the POA) when routing the one-year through ten-year NRCS Type II 24-hour design storms. See Section 3.4.3 for calculation methods, Table 3.4‑3 for design storm depths, and Table 3.4‑5 for dimensionless rainfall distribution for the NRCS Type II 24-hour design storm. Outlet controls and SMPs must also meet all design requirements of Chapter 4.

All design information developed to document compliance with the PHS Release Rate requirement must be included in the PCSMP Review Phase Submission Package. This includes but is not limited to:

  • PDF printout of completed Online Technical Worksheet;
  • Post-development drainage area plans;
  • Post-development Tc calculations (if demonstration of a Tc greater than an assumed six minutes is desired); and
  • Flow routing calculations and model inputs and results for the one-year through ten-year design storms.

Complete PCSMP Review Phase submission requirements are provided in Section 2.3.1.

3.4.2 Storm Sewer Design Requirements

All storm sewer pipes must be designed to have adequate capacity to safely convey the ten-year storm without surcharging the crown of the pipe. Pipe capacity calculations are required for all stormwater conveyance that is not connected to the roof drainage system. The designer is referred to the City of Philadelphia Plumbing Code (Plumbing Code) for guidance on sizing roof drainage systems.

If Flood Control is required, runoff from larger storms must be safely conveyed off the site, either through overland flow or a storm sewer. Runoff may not be conveyed to a neighboring property.

The Rational Method may be used when designing storm sewers. The Rational Method is a simple method for determining peak runoff discharge from both pervious and impervious cover. This method uses Rational Method runoff coefficients (C-values) based on land use, soil type, and watershed slope, to estimate peak runoff rates during different rainfall conditions. The Rational Method is primarily used to estimate runoff rates and not runoff volume.

The Rational Method may not be used for SMP design, outlet control design, or detention routing. It may be used for storm sewer capacity design, including open channel collection and conveyance systems analyses.

Required assumptions to obtain conservative results using the Rational Method include the following:

  • A runoff coefficient value of 0.35 must be used for pervious areas.
  • A runoff coefficient value of 0.95 must be used for impervious areas.
  • A precipitation intensity of 6.96 inches per hour must be used, which is the five-minute inlet concentration time in the ten-year storm event. The designer is referred to the Pennsylvania Department of Transportation (PennDOT) Drainage Manual, Chapter 7, Appendix A, Field Manual For Pennsylvania Design Rainfall Intensity Charts From the National Oceanic and Atmospheric Administration (NOAA) Atlas 14 Version 3 Data (2010 or latest) for the Intensity Duration Frequency (IDF) for Region 5 for more information.
  • For use with Manning’s Equation for calculating full channel flow, a Manning’s n value of 0.013 must be used for RCP, VCP, and CIP, and a value of 0.011 must be used for PVC and HDPE.

When designing a site’s storm sewer system, the designer must be mindful of the following requirements:

  • Length, material, size, and slope of all piping associated with stormwater conveyance and roof drainage systems must be clearly labeled on the submitted PCSMP and should be consistent with associated profiles, if provided.
  • Piping conflicts must be avoided.
  • Inlets may not be connected in series. Similarly, roof drainage systems may not tie directly into an inlet. Wye connections, or similar, may be used to ensure that inlets are offline.
  • A minimum of 12 inches of vertical clearance is required when a sanitary sewer line crosses above a storm sewer line. The sanitary sewer must be encased in concrete if the clearance is less than 12 inches.
  • Any manholes between outlet structures and sewer connections in combined sewer areas must have sanitary (non-vented) covers.
  • A cleanout must be provided, at minimum, every 75 feet, at the end of all pipes, and for all 90-degree bends.
  • If curb cuts or non-standard inlets are used to capture runoff, especially from driveways or roadways where the inlets are not in a sump condition, verification that the one-year storm will be captured by the inlet must be provided.
  • The invert elevation(s) for the proposed connection(s) to the existing City sewer and a pipe connection detail must both be provided on the submitted PSCMP.
  • The outlet culvert(s) must be right-sized to minimize impacts on PWD infrastructure.
  • All stormwater conveyance pipe material must be in compliance with the Plumbing Code.
  • A minimum cover of 36 inches must be provided over all private storm sewer pipes, in accordance with the Plumbing Code.
  • Stormwater conveyance pipes must be designed with a minimum velocity of two feet per second. Designs should attempt to maintain velocity without sacrificing SMP depth.
  • All proposed connections to the City sewer must be right-sized to convey the necessary flow while minimizing the pipe diameter.
  • All proposed connections to the City sewer must be inspected by PWD Water Transport Records. More information on this process can be found in the Sewer Connection and Repair Manual.
  • As City sewers are regularly at full capacity, two feet of clearance between the bottom of the SMP and the crown of the City sewer pipe and/or a backflow prevention device must be provided to alleviate potential flooding. If a backflow prevention device is proposed, please take into consideration the on-site point of relief during larger storms.
  • Stormwater conveyance piping and SMPs cannot receive runoff from fueling station pads for gas stations. The drainage area under a pad’s canopy must be treated by an oil/water separator then discharge directly to the sanitary sewer system.
  • Stormwater conveyance piping and SMPs that encroach onto an adjacent property require a drainage easement.

3.4.3 Calculation Methods and Design Tools

The designer will need to use various calculation methods and design tools in order to prepare an integrated stormwater management design and to demonstrate compliance with the Stormwater Regulations. The calculation methods and design tools described in this Section are used for a variety of purposes relating to integrated design including computing the amount of runoff from DCIA and other surfaces, modeling peak flow rates and drain down times, determining SMP sizing, and developing inlet/outlet control and conveyance system designs. Calculations, model inputs/outputs, and completed Online Technical Worksheet are used in the preparation of PCSMP Review Phase Submission Package, which is detailed in Section 2.3.1.

Calculation Methods

Runoff Estimation

The NRCS Curve Number Method is used to estimate site stormwater runoff from a given storm. While it is PWD’s preferred runoff estimation method, additional methods may be used at the designer’s discretion with approval from PWD.

The NRCS Curve Number Method is widely used to produce estimates of runoff volume for both pervious and impervious cover. It empirically accounts for the initial abstraction and infiltration of rainfall events on based on ground cover type characteristics. For a detailed description of the Curve Number Method, the designer is referred to Urban Hydrology for Small Watersheds (NRCS Technical Release 55).

Care must be taken to select appropriate curve number values since this calculation method is very sensitive to changes in these values. In order to obtain conservative results, separate calculations for pervious and impervious area runoff must be used. Weighted curve number values between pervious and impervious areas are not acceptable. The resulting flows can be routed, if necessary, and then summed.

Table 3.4‑2 below provides acceptable curve number values for each Hydrologic Soil Group.

Table 3.4‑2: Acceptable Curve Number Values
Cover DescriptionCurve Number for Hydrologic Soil Group
COVER TYPEHYDROLOGIC CONDITIONABCDUb*
Lawns, parks, golf courses, etc.
Poor (grass cover <50%6879868979
Fair (grass cover 50–75%)4969798469
Good (grass cover > 75%)3961748061
Brush (brush-weed-grass mixture with brush the major element)
Poor5773828673
Fair4365768265
Good3258727958
Wood-grass combination (orchard or tree farm)
Poor5773828673
Fair4365768265
Good3258727958
Woods
Poor4566778366
Fair3660737960
Good3055707755
Paved parking lots, roofs, driveways, streets, etc.9898989898
Gravel/Crushed Stone7685899189
Dirt Streets and Roads7282878987
Green Roof**8686868686
Athletic Field6879868979
Porous Pavement7070748070
Permeable Pavers7070798470
Pour-in-Place Rubber7070748070
Porous Turf7070798469
Meadow3058717858
  • * Ub refers to “Urban Land” and generally conforms to a hydrological soil group classification of B. A Ub curve number must be used on Redevelopment projects unless the engineer provides soil mapping indicative of another, more appropriate soil classification.
  • ** Existing rainfall runoff models are limited in their ability to predict runoff from green roofs since this process is dominated by percolations through a thin veneer of soil and is not surface runoff. Green roof research studies have back-calculated a range of curve number values for various storms and roof media types/thicknesses. Alternative curve number values may be applied when supported by submitted analysis and relevant references, which will be reviewed on a case-by-case basis.
Design Storms

Sizing requirements for compliance with the Stormwater Regulations have been developed using long-term computer simulations. These requirements have been translated to single event design conditions that yield roughly equivalent results.

The rainfall depths of design storms shown in Table 3.4‑3 are taken from the PennDOT Drainage Manual, Chapter 7, Appendix A, Field Manual For Pennsylvania Design Rainfall Intensity Charts From NOAA Atlas 14 Version 3 Data (2010 or latest). These totals indicate the largest depth that can be expected over the specified interval in the specified return period. These design precipitation depths are similar to those found in other standard references such as NOAA Technical Paper No. 40 or the NOAA Atlas 14; however, the designer must use the values provided in Table 3.4‑3 for their design calculations.

Table 3.4‑3: Design Precipitation Depths (in)
Return Period
DURATION1 yr2 yr5 yr10 yr25 yr50 yr100 yr
5 min0.370.450.520.580.590.650.71
10 min0.580.690.810.901.041.151.26
15 min0.710.851.001.111.291.421.56
30 min0.941.141.371.561.822.042.27
1 hr1.171.421.762.032.392.693.04
2 hrs1.391.692.122.462.933.343.90
3 hrs1.531.862.332.713.253.754.34
6 hrs1.912.312.913.404.124.705.34
12 hrs2.372.863.564.205.155.966.86
24 hrs2.833.404.224.956.107.168.43
PWD Design Storm Rainfall Distribution

The Water Quality requirement is required to be demonstrated with the new PWD Design Storm rainfall distribution, found in Table 3.4‑4 below.

This distribution is only to be used for complying with the Water Quality requirement. It is not intended to replace any assessments of Flood Control requirement compliance, Channel Protection requirement compliance, pipe sizing, or conveyance capacity for large events that are necessary for other design requirements. The NRCS Type II 24-hour storm should still be used for those purposes.

Table 3.4‑4: PWD Design Storm Rainfall Distribution
Time elapsed, minutesCumulative % of total event volume
150.000
300.002
450.012
600.037
750.058
900.079
1050.102
1200.121
1350.141
1500.166
1650.186
1800.207
1950.234
2100.258
2250.283
2400.310
2550.338
2700.364
Time elapsed, minutesCumulative % of total event volume
2850.389
3000.413
3150.437
3300.464
3450.492
3600.518
3750.543
3900.677
4050.808
4200.828
4350.853
4500.877
4650.892
4800.912
4950.933
5100.953
5250.980
5401.000
NRCS Type II 24-Hour Design Storm Rainfall Distribution

The Channel Protection, Flood Control, and PHS Release Rate requirements all require calculations using design rainfall depths distributed in a NRCS Type II 24-hour dimensionless rainfall distribution. The Type II distribution was selected not because it represents a typical event, but because it includes periods of low-intensity and high-intensity rainfall; design that uses this distribution results in SMPs that can manage a variety of event types, particularly high intensity storms.

Table 3.4‑5: Tabulated NRCS Type II 24-Hour Rainfall Distribution
TimeDimensionless Rainfall
(hr)CUMULATIVEINCREMENTAL
0.000.0000.000
2.000.0220.022
4.000.0480.026
6.000.0800.032
7.000.0980.018
8.000.1200.022
8.500.1330.013
9.000.1470.014
9.500.1630.016
9.750.1720.009
10.000.1810.009
10.500.2040.023
11.000.2350.031
11.500.2830.048
11.750.3570.074
12.000.6630.306
12.500.7350.072
13.000.7720.037
13.500.7990.027
14.000.8200.021
16.000.8800.060
20.000.9520.072
24.001.0000.048
Storm Return Periods for Large Events and Flow Bypass

At a minimum, safe conveyance of the ten-year, 24-hour design storm must be provided to and from all SMPs. Additionally, the flow that is leaving the system must meet the requirements of the Stormwater Regulations. For SMPs designed to manage smaller storms, the designer may choose to allow runoff from larger storms to bypass or quickly pass through a storage element. This is permitted as long as all applicable Stormwater Regulations, along with all SMP design requirements (Chapter 4), are met.

Flow Routing
Sheet Flow and Shallow Concentrated Flow

Sheet flow consists of shallow flow spread out over a plane. Eventually, this flow will generally concentrate into a deeper, narrower stream. While the prevalence of sheet flow in the natural environment is debated among design professionals, it does provide a reasonable mathematical basis for predicting travel time over short distances.

Urban Hydrology for Small Watersheds (TR-55) provides a sheet flow equation based on Manning’s kinematic solution. Tables of roughness values for sheet flow are available in Urban Hydrology for Small Watersheds and in Table 3.4‑6 shown below.

PWD will only accept sheet flow for the first 100 feet. After sheet flow, overland flow is considered shallow concentrated flow. Shallow concentrated flow will be considered as flowing over paved or unpaved surface for the purpose of estimating velocity.

Another method for routing overland flow is the kinematic wave solution, which can be obtained by coupling the momentum and continuity equations with simplifying assumptions and it may be solved in a computer program using numerical methods.

Table 3.4‑6: Roughness Coefficients (Manning’s n) for Sheet Flow
Surface Descrptionn1
Roof Tops0.011
Concrete0.013
Asphalt0.015
Bare Soil0.018
Sparse Vegetation20.100
Grass: Short grass prairie, Lawn0.150
Grass: Dense Grasses3, Meadow (good condition)0.240
Range (natural)0.130
Woods4: Light underbrush0.400
Woods4: Dense underbrush0.800
  • 1 The n values are a composite of information compiled by Engman (1986) and Akan (1985)
  • 2 Areas where vegetation is spotty and consists of less than 50% vegetative cover.
  • 3 Species such as weeping lovegrass, bluegrass, buffalo grass, blue grama grass, and native grass mixtures.
  • 4 Consider cover to a height of 0.1 ft. This is part of the plant cover that will obstruct sheet flow.
Channel Flow

Channel flow equations may be used to estimate flows in free-flowing gutters and swales. Manning’s equation is sufficient for these estimates on many sites. Tables of roughness values are available in Civil Engineering Reference Manual (CERM) Appendix 19.A. For channels with significant backwater, culverts which may flow under pressure, or other complex features, the St. Venant equations may be needed. These equations represent the complete solution of the momentum and continuity equations in one dimension. These may require a computer program to solve.

Time of concentration paths must be shown from the hydraulically most distant point of each drainage area to a point of interest within the drainage area, and the path must be perpendicular to each area’s contours. For reference, the post-development Tc will be less than or equal to the predevelopment Tc values, unless the site is specifically altered to increase this path. Total post-development Tc for any path must be no less than six minutes.

Storage Routing

For small storage elements where travel time within the element is insignificant, simple mass balance routing may be performed in a spreadsheet. At each time step, the change in storage volume is the difference between inflows and outflows. Inflows and outflows are a function of design and soil properties.

For larger or more complex structures, where the shape and size of the element have a significant effect on outflows, the Modified Puls (also called storage-indication) method provides more accurate routing.

Table 3.4‑7: Summary of Recommended Methods for Flow Routing
TypeMathematical ModeAppropriate For…Hand/Spreadsheet CalculationsExample Computer Programs
Overland FlowSimplified Manning kinematic solutionSheet flow path up to 100 feetYesTR‑55, TR‑20
Shallow concentrated/ NRCS empirical curveOverland flow longer than 100 feetYesTR‑55, TR‑20
Kinematic waveLarger or more complex sitesNoEPA SWMM, HEC‑HMS
Channel FlowManning equationUniform flow without backwaterYesTR‑55, TR‑20, EPA SWMM, HEC‑HMS
St. Venant equationsChannels with storage, backwaterNoEPA SWMM, HEC‑RAS
Storage RoutingSimple mass balanceSmall storage elementsYesUSACE STORM
Modified Puls/storage-indicationLarge or irregularly shaped elementsYesTR‑55, TR‑20, HEC‑HMS

Design Tools

Hydrologic Computer Software Applications

The empirical methods discussed above are most commonly applied using hydraulic and hydrologic software applications. Both public domain and proprietary programs are available. The designer is strongly encouraged to consider the assumptions and mathematical models underlying each computer program when choosing an appropriate tool to aid in design. PWD requires any stormwater model to use the minimum time step allowable by the implemented hydrologic software or a maximum of 0.01 hours.

Examples of computer programs available in the public domain are listed in Table 3.4‑8.

Table 3.4‑8: Acceptable Calculation Methods for Runoff Estimation
TypeMathematical MethodImpervious CoverExperience Modeling Soil PropertiesHand/Spreadsheet CalculationsExample Computer Programs
Empirical MethodsNRCS Curve Number MethodAnyModerate to HighYes (smaller sites)NRCS, TR‑55, TR‑20, HEC‑HMS
Infiltration Loss ModelsConstant LossAnyModerate to HighYes (smaller sites)HEC‑HMS
Green-AmptAnyHighNoEPA SWMM, HEC‑HMS
HortonAnyHighNoEPA SWMM
PWD Stormwater Plan Review Online Technical Worksheet

The PWD Stormwater Plan Review Online Technical Worksheet is designed to standardize and summarize the results of design calculations. The worksheet is generated via, and can then be accessed at any time through, the PWD Stormwater Plan Review website’s Project Dashboard. The Project Dashboard is accessed by logging into (clicking “Login Here to Apply” in the upper righthand corner of) the website.

The completed worksheet is a required part of each PCSMP Review Phase Submission Package. In addition to the worksheet, the designer must also submit relevant data, field testing results, assumptions, hand calculations, and computer program results.

The Stormwater Plan Review website also contains many other resources for the designer to use as the design and Submission Packages are prepared.

PWD Stormwater Plan Review Design Guidance Checklists

The PWD Stormwater Plan Review Design Guidance Checklists are a supplemental list of guidelines for regulatory compliance, plan creation, hydrologic modeling and calculations, and the design of specific SMPs. They are provided to assist in the formation of both sound, compliant stormwater management designs and complete PCSMP submissions.

The designer should use the checklists as guidance during the design and calculation stages or as useful quality assurance/quality control checks prior to PCSMP Review Phase submission. They can be found in Appendix F.

Standard Details

Typical construction details for several SMPs, including all of PWD’s highest-preference SMPs, such as bioinfiltration/bioretention basins, porous pavement, and green roof, and for SMP-related structures, such as cleanouts, observations wells, and outlet control structures, are available for download in AutoCAD (*.dwg) format in Appendix L of this Manual. These Standard Details incorporate design specifications pursuant to each SMP’s respective design and material requirements. The designer is encouraged, not required, to use them for PCSMP creation when possible.

For bioinfiltration/bioretention basins, the minimum requirements set forth in the Standard Detail must be used, along with the Bioinfiltration/Bioretention Basin Sizing Table, to ensure that bioinfiltration/bioretention SMPs can be fully designed and approved for Water Quality compliance without knowledge of infiltration feasibility under a Surface Green Review. This allows for postponement of infiltration testing until construction of the development project. The designer is referred to Section 4.1 for more information on bioinfiltration/bioretention SMPs and to Section 2.4 for more information on Expedited PCSMP Reviews. Additional PWD resources can be found in the PWD Development Services Resource Directory.

Jump to Top